Roll No.
Total No. of Questions : 07
B.Com(Sem.–3rd)
OPERATION
RESEARCH
Subject
Code : BCOP-304
Paper
ID : [B1127]
Time : 3 Hrs.
INSTRUCTION TO CANDIDATES :
1.
SECTION-A is COMPULSORY consisting of TEN questions carrying
TWO
marks each.
2.
SECTION-B contains SIX questions carrying TEN marks each and students has to
attempt any FOUR questions.
SECTION-A
l.
Write briefly :
(a)
Define Operations Research
(b)
What do you understand by degeneracy in LPP?
(c)
Briefly explain Hungrarian Assignment method.
(d)
What is Critical Path? State the necessary conditions of Critical Path?
(e)
Describe the Maximin and Minimax Principle of Game Theory.
(f)
Define EOQ and discuss its assumptions.
(g)
What are the applications of Sequencing Problem?
(h)
What do you understand by Safety Stock?
(i)
Discuss Primal Dual relationship.
(j)
Distinguish between Free, Interfering and Independent floats.
SECTION-B
2.
What is Linear Programming? Discuss the applications of Linear Programming.
3.
Solve the following transportation problem for maximum profit.
Warehouse
|
Per Unit Profit (Rs.)
|
||||
Market
|
|||||
|
A
|
B
|
C
|
D
|
|
X
|
12
|
18
|
6
|
25
|
|
Y
|
8
|
7
|
10
|
18
|
|
Z
|
14
|
3
|
11
|
20
|
Availability at warehouses
|
Demand in the markets
|
X : 200 units
|
A : 180 units
|
Y : 500 units
|
B : 320 units
|
Z : 300 units
|
C : 100 units
|
|
D : 400 units
|
4.
What is the meaning and functions of inventory control? Discuss ABC analysis
of inventory control.
5.
Solve the following game using graphical Approach:
B’s’Strategy
|
|||||
A’s strategy
|
|
B1
|
B2
|
B3
|
B4
|
|
A1
|
8
|
5
|
-7
|
9
|
|
A2
|
-6
|
6
|
4
|
-2
|
6.
Find the sequence that minimizes the total elapsed time required (T) in completing
the following jobs. Each job is processed in the order ABC. Also,
calculate T.
Job
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
Machine A
|
10
|
8
|
12
|
6
|
9
|
11
|
9
|
Machine B
|
6
|
4
|
6
|
5
|
3
|
4
|
2
|
Machine C
|
8
|
7
|
5
|
9
|
10
|
6
|
5
|
7.
(a) Draw a network corresponding to the following information.
(b)
Find the earliest and latest scheduling times of various activities.
(c)
Also obtain the total, interfering, free and independent floats for each of
the activities.
Activity
|
Time (days)
|
1-2
|
8
|
1-3
|
2
|
1-4
|
6
|
1-5
|
12
|
2-4
|
5
|
2-7
|
9
|
3-5
|
3
|
3-6
|
7
|
4-10
|
4
|
5-11
|
10
|
6-7
|
2
|
6-8
|
10
|
7-10
|
12
|
8-9
|
3
|
8-10
|
6
|
9-12
|
8
|
10-12
|
18
|
10-14
|
9
|
11-12
|
7
|
11-14
|
4
|
12-13
|
11
|
13-14
|
4
|